Back to civil-engineering MCQs

This civil-engineering MCQ highlights a frequently tested idea from Civil Engineering. Reviewing "For the construction of water bound macadam roads, the correct sequence of operations after spreading coarse aggregates is________________?" strengthens conceptual clarity and improves readiness for real exam scenarios.

For the construction of water bound macadam roads, the correct sequence of operations after spreading coarse aggregates is________________?

A
dry rolling, wet rolling, application of screening and application of filler
B
dry rolling, application of filler, wet rolling and application of screening
C
dry rolling, application of screening, wet rolling and application of filler
D
dry rolling, application of screening, application of filler and wet rolling
By: Admin
Correct

How to Study This civil-engineering Question

This question belongs to the civil-engineering preparation set on McqsBase. Read the question carefully, compare every option, and focus on why the correct answer is better than the distractors. This method improves recall and helps you handle similar MCQs in FPSC, SPSC, PPSC, NTS, CSS, PMS, and university entry tests.

For stronger preparation, revise the related topic after solving the MCQ, then attempt more questions from the same category. Repeated practice builds speed, accuracy, and confidence for one-paper exams where small wording differences can change the answer.

Share this Question