What characteristic best describes the cost baseline?

A
Total budget for the project
B
Time phased budget for the project
C
Total budget for the project including the contingency budget
D
Total budget for the project including the contingency budget and the management reserve
By: Admin
Correct

How to Study This civil-engineering Question

This question belongs to the civil-engineering preparation set on McqsBase. Read the question carefully, compare every option, and focus on why the correct answer is better than the distractors. This method improves recall and helps you handle similar MCQs in FPSC, SPSC, PPSC, NTS, CSS, PMS, and university entry tests.

For stronger preparation, revise the related topic after solving the MCQ, then attempt more questions from the same category. Repeated practice builds speed, accuracy, and confidence for one-paper exams where small wording differences can change the answer.

Share this Question