This civil-engineering MCQ highlights a frequently tested idea from Civil Engineering. Reviewing "In testing a pile by load test, pile platform is loaded with one and half times the design load and a maximum settlement is noted. The lo..." strengthens conceptual clarity and improves readiness for real exam scenarios.

In testing a pile by load test, pile platform is loaded with one and half times the design load and a maximum settlement is noted. The load is gradually removed and the consequent rebound is measured. For a safe pile, the net settlement (i.e. total settlement minus rebound) per tonne of test load should not exceed________________?

A
10 mm
B
15 mm
C
20 mm
D
25 mm
By: Admin
Correct

How to Study This civil-engineering Question

This question belongs to the civil-engineering preparation set on McqsBase. Read the question carefully, compare every option, and focus on why the correct answer is better than the distractors. This method improves recall and helps you handle similar MCQs in FPSC, SPSC, PPSC, NTS, CSS, PMS, and university entry tests.

For stronger preparation, revise the related topic after solving the MCQ, then attempt more questions from the same category. Repeated practice builds speed, accuracy, and confidence for one-paper exams where small wording differences can change the answer.

Share this Question