This maths MCQ highlights a frequently tested idea from Maths. Reviewing "C takes 6 days to complete half of a work and D takes 5 days to complete 1/3rd of the same work. They take turns to complete the task. If..." strengthens conceptual clarity and improves readiness for real exam scenarios.

C takes 6 days to complete half of a work and D takes 5 days to complete 1/3rd of the same work. They take turns to complete the task. If C works for the first 4 days, in how many days will D complete the rest of the work without the help of C?

A
10 days
B
12 days
C
8 days
D
9 days
By: Anonymous
Correct

How to Study This maths Question

This question belongs to the maths preparation set on McqsBase. Read the question carefully, compare every option, and focus on why the correct answer is better than the distractors. This method improves recall and helps you handle similar MCQs in FPSC, SPSC, PPSC, NTS, CSS, PMS, and university entry tests.

For stronger preparation, revise the related topic after solving the MCQ, then attempt more questions from the same category. Repeated practice builds speed, accuracy, and confidence for one-paper exams where small wording differences can change the answer.

Share this Question